Skip to main content
Normal View

Schools Building Projects Status

Dáil Éireann Debate, Tuesday - 11 June 2019

Tuesday, 11 June 2019

Questions (275)

Brendan Ryan

Question:

275. Deputy Brendan Ryan asked the Minister for Education and Skills the number of tenders received by the closing date of 7 June 2019 for the construction of a school (details supplied); when the tender report is expected; when a letter of intent will issue; when the contractor will be on site; and if he will make a statement on the matter. [24022/19]

View answer

Written answers

The project to which the Deputy refers has been devolved to Kildare and Wicklow Education & Training Board.

We understand from KWETB that tenders have been invited from the shortlisted contractors and the closing date for receipt of same has been extended to 21st June 2019.  It is expected that a Tender Report will be issued to the Department shortly thereafter. 

A Letter of Intent will issue when the Department has approved the Tender Report.  The project will then proceed to construction.