Skip to main content
Normal View

Schools Building Projects Status

Dáil Éireann Debate, Tuesday - 9 July 2019

Tuesday, 9 July 2019

Questions (211)

Kevin O'Keeffe

Question:

211. Deputy Kevin O'Keeffe asked the Minister for Education and Skills the status of project works at a school (details supplied) in County Cork; and if the works are on schedule to be completed for the commencement of the 2019/2020 academic year. [29205/19]

View answer

Written answers

The Deputy will be aware that the delivery of this project has been devolved to Cork Education & Training Board (CETB).

Construction work to complete this project commenced in mid April. It remains on schedule to be completed for the start of the 2019/20 academic year.  