Question:185. Deputy Alan Farrell asked the Minister for Education and Skills the status of the provision of a new school building for a school (details supplied); and if he will make a statement on the matter. [37110/19]
View answerDáil Éireann Debate, Tuesday - 17 September 2019
185. Deputy Alan Farrell asked the Minister for Education and Skills the status of the provision of a new school building for a school (details supplied); and if he will make a statement on the matter. [37110/19]
View answerThe building project for the school referred to by the Deputy is included in my Department’s Construction Programme which is being delivered under the National Development Plan.
This project is one of the school building projects on my Department’s ADAPT 2 (Accelerated Delivery of Architectural Planning & Tendering) Programme. My Department has completed the process of appointing a Project Manager for the ADAPT 2 Programme, which currently contains 16 school building projects.
The appointment of a Design Team (Architect, Quantity Surveyor, Civil & Structural Engineer, Mechanical & Electrical Engineer and Project Supervisor for the Design Process) for the school in question will commence in the coming weeks with the procurement process being carried out by the appointed Project Manager.