Garda Station Refurbishment

Dáil Éireann Debate, Tuesday - 1 October 2019

Tuesday, 1 October 2019

Questions (169)

Niamh Smyth

Question:

169. Deputy Niamh Smyth asked the Minister for Public Expenditure and Reform the reason for the delay in commencing works on Bailieborough Garda station, County Cavan; and if he will make a statement on the matter. [39521/19]

View answer

Written answers

There have been no delays in progressing this project.  Following site acquisition, the required Part 9 Planning application was lodged, with Planning Permission being granted in December 2018.  A full Design Team was appointed thereafter and this team is developing the full suite of Tender documentation required for the project.  It is envisaged that the procurement process for the works will commence later in 2019 with contracts being signed and work commencing on site in 2020. Supplementary Information