Skip to main content
Normal View

Rail Network Expansion

Dáil Éireann Debate, Thursday - 24 October 2019

Thursday, 24 October 2019

Questions (259)

Marc MacSharry

Question:

259. Deputy Marc MacSharry asked the Minister for Transport, Tourism and Sport the status of the review of the western rail corridor. [44175/19]

View answer

Written answers

As the Deputy is aware, Project Ireland 2040 committed to conducting an independent review of a possible extension to the Western Rail Corridor (WRC).

In line with that commitment an external company was commissioned to prepare a financial/economic appraisal and business case on proposals for extending the existing WRC from Athenry to Claremorris.

I understand the work is almost complete and I expect the business case will then be submitted to my Department where it will be reviewed in line with the requirements of the Public Spending Code. 

As stated in Project Ireland 2040 if the findings of the review are approved by Government, the project will be prioritised during the lifetime of the National Development Plan. 

Top
Share