Skip to main content
Normal View

Air Corps

Dáil Éireann Debate, Thursday - 28 November 2019

Thursday, 28 November 2019

Questions (63)

Thomas P. Broughan

Question:

63. Deputy Thomas P. Broughan asked the Taoiseach and Minister for Defence if the upgrade of accommodation facilities at Casement Aerodrome, Baldonnel, is fully completed; if not, when the works will be completed; and if he will make a statement on the matter. [49557/19]

View answer

Written answers

The contract for the refurbishment of the Apprentice Hostel Accommodation Block at Casement Aerodrome, Baldonnel is well advanced. This will provide class rooms, auditorium, recreational and improved living in accommodation for 75 personnel. Works are progressing well and the project is due to be completed in early 2020 at a cost of €3.3m.