Schools Building Projects Status

Dáil Éireann Debate, Thursday - 5 March 2020

Thursday, 5 March 2020

Questions (309)

Thomas Byrne

Question:

309. Deputy Thomas Byrne asked the Minister for Education and Skills the progress made on securing a new permanent building for a school (details supplied); and if he will make a statement on the matter. [3665/20]

View answer

Written answers

The school building project for the school referred to be the Deputy has been assigned for delivery under my Department's Design and Build programme.  The brief for this project is a 16 classroom school with 2 classroom SEN.  The project is currently in architectural planning.  Site surveys have commenced in advance of preparing the Planning Application which will be the next key milestone in the progression of the project.  Once all statutory approvals have been secured, the project will proceed to tender and construction stages.