National Broadband Plan

Dáil Éireann Debate, Wednesday - 27 May 2020

Wednesday, 27 May 2020

Questions (723)

Michael Healy-Rae

Question:

723. Deputy Michael Healy-Rae asked the Minister for Communications, Climate Action and Environment the status of the national broadband plan; when work will commence; and if he will make a statement on the matter. [7460/20]

View answer

Written answers

The government is committed to delivering high speed broadband to every home, farm, business and school in Ireland.

The National Broadband Plan (NBP) contract was signed with National Broadband Ireland (NBI) in November 2019, to roll out a high speed and future proofed broadband network within the Intervention Area which covers 1.1 million people living and working in the nearly 540,000 premises, including almost 100,000 businesses and farms along with 695 schools.

The NBP network will offer users a high speed broadband service with a minimum download speed of 150Mbps from the outset. By the end of next year, NBI plans to pass in the region of 115,000 premises, with 70,000 - 100,000 passed each year thereafter until rollout is completed. All counties will see premises passed in the first 2 years and over 90% of premises in the State will have access to high speed broadband within the next four years.

NBI contractors commenced survey work in January to inform the detailed designs needed for each deployment area. Further information on deployment activities can be found on the NBI website www.nbi.ie .

To support remote working and connected communities, approximately 300 Broadband Connections Points (BCPs) were identified by Local Authorities to be connected to high speed broadband this year. This will assist communities to quickly get free public access to high speed broadband in advance of the main NBP deployment. The planned BCP locations, including schools, library hubs, local sports facilities and other public places are available to view on the High Speed Broadband Map on the Department’s website www.broadband.gov.ie. The BCP delivery project is well underway and surveying of the BCP locations is progressing which will facilitate detailed design and installation. BCP locations are subject to change and a number of the premises initially identified are in the process of being replaced with alternative locations. The remaining BCPs remain on track for delivery by the end of 2020.

The BCPs in identified public places will leverage the high speed broadband connection through a range of measures and initiatives, for example providing free public Wi-Fi, some will also have hot-desks, and some will be digital hub business centres where digital training, business information events and other SME supports are organised.