Dáil Éireann Debate, Thursday - 24 September 2020

Thursday, 24 September 2020

Questions (145)

Colm Burke

Question:

145. Deputy Colm Burke asked the Minister for Education if the building of a new school (details supplied) has completed the tender stage; if the contract has been awarded; if so, when building work will commence; and if she will make a statement on the matter. [26118/20]

View answer

Written answers

The major project for the construction of the new school building for the school referred to by the Deputy is at an advanced stage of the tender process. My Department is currently awaiting a Tender Report from the school and its Design Team, which is due to be submitted before the end of this month.

Subject to no issues arising, it is envisaged that construction should commence late this year with a contract duration of approximately 32 months.