The project referred to by the Deputy when complete will provide a three Storey 16 classroom Primary School building, including a two classroom special education needs base.
The design also includes a general-purpose hall, support teaching spaces and ancillary accommodation, external junior play areas, secure SEN hard and soft play area and a sensory garden. The proposed project incorporates associated car parking, access road, pedestrian access, bicycle lane, construction of 2 no. external ball courts, landscaping, connection to public services and all associated site works.
It is anticipated that the project will proceed to tender in the first half of 2021 with construction expected to start in late 2021 and the estimated construction period for the project will be approximately 48 weeks.