The National Development Plan 2021-2030 which was published on 4th October 2021, provides capital funding of over €4.4bn for investment in school infrastructure during the period 2021 to 2025.
This investment will build on the good progress being made on adding capacity to cater for demographic changes and provision for children with special educational needs. This investment will also facilitate an increased focus on the modernisation of existing school stock and help transition the school system for an era of net zero carbon by 2050.
Approximately 1,200 school building projects are currently in progress across the various stages of planning, design, tender and construction – most of which are expected to be either under construction or completed in the period 2021 to 2025. These projects, with a monthly status update, are listed on gov.ie
Over 200 of these projects are currently at construction, with most of these scheduled for completion in 2022.