Darren O'Rourke
Question:311. Deputy Darren O'Rourke asked the Minister for Public Expenditure and Reform the amount that the OPW spend on the refurbishment of Navan Garda station. [53044/21]
View answerDáil Éireann Debate, Tuesday - 2 November 2021
311. Deputy Darren O'Rourke asked the Minister for Public Expenditure and Reform the amount that the OPW spend on the refurbishment of Navan Garda station. [53044/21]
View answerThe Office of Public Works can confirm that a contract for the refurbishment of Navan Garda Station to the value of €1,638,816.32 excluding vat was awarded on 15th April 2021. The total expenditure to date for the project is €239,864.66 which includes vat and consultancy fees.
The project is co- funded by the Office of Public Works and An Garda Síochána.