Skip to main content
Normal View

Defence Forces

Dáil Éireann Debate, Wednesday - 9 February 2022

Wednesday, 9 February 2022

Questions (84)

Sorca Clarke

Question:

84. Deputy Sorca Clarke asked the Minister for Defence if his Department is undertaking a feasibility study on the future use of Cathal Brugha Barracks as correspondence confirms that the Land Development Agency is not; if his attention has been drawn to that the fact that it has been confirmed that the Land Development Agency has not had engaged with his Department or the Department of Housing, Local Government and Heritage on this issue; and if he will make a statement on the matter. [6958/22]

View answer

Written answers

My Department has secured funding, under the Housing For All implementation fund, to engage consultants to carry out a cost-benefit analysis and feasibility study in relation to the viability of relocating Cathal Brugha Barracks to another city centre location or location on the outskirts of Dublin City.

It should be noted that this is an exploratory exercise, the purpose of which is to allow for the identification of all the implications and practicalities of such a possible relocation. The completion of the study will facilitate an informed debate on the feasibility, costs and indeed the practicality of a relocation of DF operations from Cathal Brugha Barracks.

My Department, together with the Defence Forces, is now developing a tender proposal and will go to the market in the coming weeks. This study will compromise three fundamental aspects:

- Consideration of Whole Life Cycle Costs and Benefits– including new land acquisition costs and provision of a new build Barracks;

- Assessment of the operational and security implications and risks associated with a relocation;

- Determination as to the feasibility of relocating incorporating internal comparators as to how other States manage the threats & risks to their capital infrastructure.

This project should take some 9 to 12 months to complete and all relevant Stakeholders will be briefed as this project progress.