Neale Richmond
Question:1035. Deputy Neale Richmond asked the Minister for Education the status of the provision of a permanent site for a school (details supplied); and if she will make a statement on the matter. [30422/22]
View answerDáil Éireann Debate, Tuesday - 14 June 2022
1035. Deputy Neale Richmond asked the Minister for Education the status of the provision of a permanent site for a school (details supplied); and if she will make a statement on the matter. [30422/22]
View answerThe acquisition of the site for the school referred to by the Deputy was completed in 2020.
The building project for the school is being delivered under my Department's Design and Build programme. This delivery programme uses a professional external Project Manager to progress the project through the relevant stages of architectural planning, tender and construction.
The Letter of Acceptance issued to the successful Contractor on 18th May 2022 commencing the school building contract and the contractor has mobilised on site.