Schools Building Projects

Dáil Éireann Debate, Thursday - 30 June 2022

Thursday, 30 June 2022

Questions (199)

Bernard Durkan

Question:

199. Deputy Bernard J. Durkan asked the Minister for Education the extent to which each school building project in respect of school provision requirements at primary and second level in Celbridge, County Kildare is progressing whether at planning or implementation level in line with the requirements as set out by each school authority and in keeping with previously anticipated deadlines; and if she will make a statement on the matter. [35201/22]

View answer

Written answers

My Department utilises a Geographic Information System (GIS) to support its strategic planning for capital investment. Where the geo-spatial assessment of demand and capacity in an area indicates that additional provision is required my Department considers the options of extending the capacity of a school or schools, or of providing a new school or schools. The timing and duration of the accommodation need is also considered in determining the optimum accommodation solution – for example a short-term accommodation requirement does not require a long-term accommodation solution.

My Department has a large pipeline of projects for delivery under the school building programme. The main elements of this pipeline currently involve in excess of 1,300 school building projects for delivery under the Department’s Large Scale and Additional Accommodation Scheme. These projects are currently in progress across the various stages of planning, design, tender and construction. There are currently in excess of 250 school building projects at construction (on site) with a continuous stream of other projects at or near the tendering stage. Most of which are expected to be either under construction or completed in the period up to 2025 and are being progressed as quickly as possible.

It is anticipated that 150 to 200 school building projects will be completed annually during the 2022 to 2025 period.

A project to provide for three schools (St Raphael’s Special School, Scoil Naomh Padraig, Celbridge Community School) on a single campus in Celbridge has been devolved to the National Development Finance Agency (NDFA) for delivery as part of a programme of school building projects.

A letter was issued to the school on the 18th February 2022. This letter advised the school that the NDFA will write to them once all the preparation works are complete to make arrangements to meet to discuss the project brief for the school and the expected timeline for the project.

Conveyancing for the site acquisition for this project is at an advanced stage. Due to the commercially sensitive nature of site acquisitions generally, it is not possible to comment further at this stage.

The current status of approved projects is listed on a county by county basis on www.gov.ie and is updated on a monthly basis to reflect their progress through the various stages.