Schools Building Projects

Dáil Éireann Debate, Tuesday - 26 July 2022

Tuesday, 26 July 2022

Questions (1105)

Seán Sherlock

Question:

1105. Deputy Sean Sherlock asked the Minister for Education the status of works of a building project (details supplied); and if timelines have been established for completion and occupation by pupils. [40836/22]

View answer

Written answers

The Letter of Acceptance for the school referred to by the Deputy issued to the preferred tenderer on the 18th May 2022, this commenced the school building contract.

The construction programme is 84 weeks. Due to complexities on site, the project will be handed over in three phases, phase one will take 52 weeks, phase two 24 weeks and phase three 8 weeks.