91. Deputy Claire Kerrane asked the Minister for the Environment, Climate and Communications the number of premises connected in the broadband roll-out in counties Roscommon and Galway to date in 2022, in tabular form. [40232/22]

View answer

Written answers

The National Broadband Plan (NBP) State led Intervention will be delivered by National Broadband Ireland (NBI) under a contract to roll out a high speed and future proofed broadband network within the Intervention Area which covers 1.1 million people living and working in almost 560,000 premises, including almost 100,000 businesses and farms along with some 679 schools.

I am advised by National Broadband Ireland (NBI) that, as of 15 July 2022, over 313,600 premises are design completed and over 70,700 premises can order or pre-order a high-speed broadband connection across 23 counties. NBI has further advised that over 63,600 premises are passed with a high speed fibre broadband service across 23 counties and available for immediate connection. Construction is underway across 26 counties demonstrating that the project is reaching scale. To date, the level of connections is increasing on a daily basis and is in line with projections with some areas exceeding expectations. NBI has advised that in County Roscommon there are currently 4,191 premises passed with a high speed fibre broadband service and available for immediate connection and in County Galway there are 8,069 premises passed.

Further details are available on specific areas within County Roscommon and County Galway through the NBI website which provides a facility for any premises within the intervention area to register their interest in being provided with deployment updates through its website www.nbi.ie. Individuals who register with this facility will receive regular updates on progress by NBI on delivering the network and specific updates related to their own premises as works commence. NBI has a dedicated email address, reps@nbi.ie, which can be used by Oireachtas members for specific queries.

NBI has made recent improvements to their website to enhance the provision of information to Oireachtas members. NBI has now completed a suite of changes, creating a portal that will serve as a means for Oireachtas members to proactively search for information relevant to their county/local area. The portal provides an up-to-date picture of NBI’s deployment schedule across the 227 Deployment Areas (DAs) in all 26 counties. A particular county can be selected to view an update of the overall number of premises in the Intervention Area, the overall NBP investment in the county, the number of premises passed to date and the status of each of the Deployment Areas with the anticipated date for connection over the lifetime of the project. The dedicated webpage can be accessed here: www.nbi.ie/reps.

Broadband Connection Points (BCPs) are a key element of the NBP providing high speed broadband in every county in advance of the roll out of the fibre to the home network. Some 657 BCP sites have been installed by NBI, as of 15 July 2022, and the high speed broadband service will be switched on in these locations through service provider contracts managed by the Department of Rural and Community Development for publicly accessible sites and the Department of Education for school BCPs. In County Roscommon 9 BCPs have been installed by NBI to date. In County Galway 20 BCPs have been installed. Further details can be found at nbi.ie/broadband-connection-points/.

In County Roscommon 6 schools have been installed by NBI to date for educational access. In County Galway 32 schools have been installed. My Department continues to work with the Department of Education to prioritise schools with no high speed broadband, within the Intervention Area. Further details of schools in scope are available on the NBI website at nbi.ie/primary-schools-list/