Schools Building Projects

Dáil Éireann Debate, Thursday - 15 September 2022

Thursday, 15 September 2022

Questions (233)

Seán Haughey

Question:

233. Deputy Seán Haughey asked the Minister for Education if the grant awarded to a school (details supplied) under the summer works scheme in 2019 will be increased given that the cost of the heating works have substantially increased since then; and if she will make a statement on the matter. [45236/22]

View answer

Written answers

St David’s CBS in Artane was approved funding under the Summer Works Scheme for the upgrade of the heating system at the school.

Following a tender process, the school authority appointed a consultant to progress the project. When the consultant attended the site to conduct survey works related to the proposed heating upgrade project, the consultant advised that a full review and assessment of the building fabric was required to be carried out by a specialist, prior to any heating upgrade works being started. It should be noted that this school is a protected structure.

The project is currently being considered within the Dept. and a decision on same will be made in the near future. The Dept. will be in contact with the school directly thereafter.