Dáil Éireann Debate, Tuesday - 20 September 2022

Tuesday, 20 September 2022

Questions (437, 438)

Matt Shanahan

Question:

437. Deputy Matt Shanahan asked the Minister for Further and Higher Education, Research, Innovation and Science if he will provide a schedule of the dates of each of the project milestones with respect to the Coonagh Campus development undertaken by Limerick Institute of Technology / Technological University of the Shannon since the project's inception. [45509/22]

View answer

Matt Shanahan

Question:

438. Deputy Matt Shanahan asked the Minister for Further and Higher Education, Research, Innovation and Science if he will provide a schedule of formal correspondence between the Department, the Higher Education Authority and Limerick Institute of Technology / Technological University of the Shannon with respect to the Coonagh Campus development undertaken by LIT/TUS since the project's inception. [45510/22]

View answer

Written answers

I propose to take Questions Nos. 437 and 438 together.

As the Deputy will be aware, in accordance with the Public Spending Code, the Project Lifecycle refers to the series of steps and activities which are necessary to take the proposal from concept to completion and evaluation.

The Coonagh Campus project was split into two components; the ‘Enabling / Shell & Core’ works and the 'Fit out ' works. I have set out the main stages and dates in the table below in respect of each of these components.

Project Element

Tender Commencement

Construction Commencement

Construction Completion

Project Review & Reporting Period

Enabling Shell & Core

July 2017

July 2018

February 2020

February 2023

Fit Out

TBC

TBC

TBC

TBC

The table attached sets out the key communications and milestones relating to the project at TUS-Coonagh Campus, from the decision to acquire the site up to the current Fit Out phase of the project. It is important to note that since the inception of the TUS-Coonagh Project and between the milestone dates referenced in the table there was extensive engagement between the Institute, HEA DFHERIS, resolution of queries in relation to procurement, tendering, etc. However given the volume of these and the timeframe required to respond my Department have focused on the key milestones of the project.

Documents/Key Milestones

Date

Approval of site purchase at cost of €3.5m

Nov 2015

Economic Impact of LIT Campus Report

June 2016

ABP grant planning

July 2017

Procurement process commenced for the ‘Enabling / Shell & Core Contract’

July 2017

DES Approval for development project

June 2018

Contract awarded for ‘Enabling Shell and Core contract’ by LIT and commenced onsite

July 2018

The Enabling Shell and Core contract’contract reached substantial completion

February 2020

HEA Options and Recommendations Report submitted to DFHERIS for fit-out phase

Dec 2020

DFHERIS approval for Fit-out commencement

May 2022

Question No. 438 answered with Question No. 437.