The Defence Forces Infrastructure Development Plan (IDP) in 2020 sets out a programme of anticipated project delivery based on requirements identified from a survey of all DF installations and on the achievement of the high-level goals set out in White Paper 2015.
The Deputy may wish to note, as advised by the military authorities, that the following maintenance and refurbishment works were undertaken on a devolved basis at Custume Barracks for the 2020- 2022 period.
Nature of works completed
|
Contract Value
|
2022 Roof Repairs
|
€22,999.64
|
Refurbishment of Abultions
|
€32,915.00
|
2021 External refurbishment (Roads & Carparking)
|
€139,112.64
|
Painting & Decoration
|
€59,833.17
|
2020 External refurbishment (Roads & Carparking)
|
€94,607.74
|
Refurbishment of offices
|
€22,546.00
|
Ventilation and screening upgrade
|
€38,817.00
|
Roof & chimney repairs
|
€94,108.63
|
General refurbishment
|
€51,357.73
|
Building energy management system upgrade
|
€164,787.25
|
Total
|
€721,084.80
|