Schools Building Projects

Dáil Éireann Debate, Tuesday - 4 October 2022

Tuesday, 4 October 2022

Questions (379)

Ivana Bacik

Question:

379. Deputy Ivana Bacik asked the Minister for Education the status of the new permanent building for a school (details supplied). [48112/22]

View answer

Written answers

The permanent building project for the post-primary school referred to by the Deputy is being delivered under my Department's Design and Build programme. This delivery programme uses a professional external Project Manager to progress the project through the relevant stages of architectural planning, tender and construction. 

The Grant of Planning decision was received from An Bord Pleanála in February 2021. 

My Department’s Project Manager together with their Design Team are engaged in the preparation of tender documentation for the project. Once this stage is complete, the project will then proceed to tender stage.  It is intended that the project will be included in the next bundle of projects to proceed to tender later this year.