Flood Risk Management

Dáil Éireann Debate, Tuesday - 4 October 2022

Tuesday, 4 October 2022

Questions (97)

Pádraig O'Sullivan

Question:

97. Deputy Pádraig O'Sullivan asked the Minister for Public Expenditure and Reform if he will provide an update on the selection of a contractor for the Glashaboy flood relief scheme; and if he will make a statement on the matter. [48152/22]

View answer

Written answers

The Glashaboy River Flood Relief Scheme at Glanmire / Sallybrook, Cork is being progressed by Cork City Council. The Office of Public Works (OPW) in partnership with Cork City Council are engaging proactively to progress the flood relief scheme for Glanmire.

The Glashaboy Flood Relief Scheme was confirmed in January 2021 by the Minister for Public Expenditure and Reform under the Arterial Drainage Acts 1945 to 1995. The scheme is being funded from the €1.3 billion in flood relief measures under the National Development Plan to 2030, and as part of Project Ireland 2040. Provision for the total project budget for this scheme is included in the Office of Public Works multi annual capital allocation.

The Glashaboy River Flood Relief Scheme will protect 103 properties from a significant risk of flooding.

The tender documentation for the procurement and appointment of a contractor was issued in September 2021 with a return date of 24th January 2022. Unfortunately, Cork City Council was not in a position to appoint a Contractor for the works on foot of this procurement process. However, Cork City Council is proceeding towards issuing updated Tender Documents in Q4 2022 and is working with key project partners to minimise the overall delay in the completion of these works. I hope to visit Cork shortly and will be discussing this matter with the Council.