326. Deputy Catherine Murphy asked the Minister for Public Expenditure and Reform the date on which the OPW completed its hand-over of the new Garda security and operations centre building on Military Road to An Garda Síochána. [55607/22]

View answer

Written answers

Substantial Completion of the new Garda security and operations centre building on Military Road was granted to the Principal Contractor on Friday 21 October 2022. the Office of Public Works handed over the new Garda Security and Operations Centre on 2nd November 2022 to An Garda Síochána. The Military Road building will provide modern, fit for purpose facilities for An Garda Síochána.