Question:601. Deputy Sean Sherlock asked the Minister for Education the status of building underway at a school (details supplied); and the timelines in place for opening to students. [55248/22]
View answerDáil Éireann Debate, Tuesday - 8 November 2022
601. Deputy Sean Sherlock asked the Minister for Education the status of building underway at a school (details supplied); and the timelines in place for opening to students. [55248/22]
View answerThe Letter of Acceptance (LOA) issued to the preferred tenderer on the 31st May 2022 commencing the school building contract for the school referred to by the Deputy.
The construction programme is 70 weeks with the new 1,000 post-pupil school anticipated to be completed in Q3/Q4 2023. My Department is in discussions with the patron with regard to any short-term interim accommodation requirements for 2023 pending delivery of the permanent school.
My Department will continue to keep the school authorities informed of the construction programme.