Skip to main content
Normal View

Housing Provision

Dáil Éireann Debate, Wednesday - 18 January 2023

Wednesday, 18 January 2023

Questions (517)

Eoin Ó Broin

Question:

517. Deputy Eoin Ó Broin asked the Minister for Housing, Local Government and Heritage the average cost of one-, two-, three-, and four-bedroom social houses and one-, two-, and three-bedroom social apartments that were completed in 2022; and the average cost for the same set of units for tender contracts signed in 2022, in tabular form. [63756/22]

View answer

Written answers

The relevant details are being compiled and will be provided to the Deputy in accordance with Standing Orders

The following deferred reply was received under Standing Order 51.
My Department assesses, approves and records local authority social housing delivery on a project basis, rather than on the basis of individual unit types. As Social Housing Investment Programme (SHIP) funded construction projects by local authorities must, like all publicly-funded construction programmes, comply with the Public Spending Code and Capital Works Management Framework, my Department periodically issues Unit Cost Ceilings (UCCs) for each local authority area, for use as a key benchmark for the development and costing of scheme designs at capital appraisal stage. While not a record of actual delivery costs, UCCs are based on an analysis of returned data from tendered social housing schemes.
To monitor tender cost trends and to inform the UCCs levels, my Department analyses the tender data for the construction cost element of new build schemes approved under the SHIP four stage approval processes for each unit type, where sufficient information is available to allow such costs to be extrapolated and where the information available is appropriate for comparison purposes.
Outlined in the tables below are average construction costs (incl. VAT) per unit type, recorded as part of the aforementioned analysis for projects tendered in each of the years 2020 to 2021. The tables also set out the range of costs that make up this average for each unit type. The range of costs recorded vary, depending on design, location and on the level of abnormal requirements for each scheme, for instance existing site conditions, demolitions, service diversions and site access requirements. Abnormal costs are also separately identified in the tables below.

2020

Construction Costs (incl abnormals)

Abnormal Costs

Average Cost Per Unit €

Range of Costs per Unit €

Average Cost Per Unit €

Range of costs per unit €

1bed house

184,435

139k - 237k

24,949

3k - 46k

2bed house

193,665

129k - 263k

24,287

1k - 66k

3bed house

211,518

152k - 342k

24,602

1k - 66k

4bed house

262,311

205k - 321k

40,196

15k - 66k

1bed apartment

198,719

169k - 269k

22,875

24k - 54k

2bed apartment

230,691

198k - 306k

16,337

7k - 54k

3bed apartment

N/A

N/A

N/A

N/A

2021

Construction Costs (incl abnormals)

Abnormal Costs

Average Cost Per Unit €

Range of Costs per Unit €

Average Cost Per Unit €

Range of costs per unit €

1bed house

180,375

143k - 234k

21,499

7k - 41k

2bed house

235,253

144k - 347k

29,893

6k - 64k

3bed house

248,105

162k - 427k

25,860

4k - 68k

4bed house

302,311

190k - 457k

33,302

11k - 44k

1bed apartment

212,765

179k - 276k

40,557

30k - 58k

2bed apartment

244,296

187k - 325k

43,113

34k - 64k

3bed apartment

306,096

302k - 312k

50,451

46k - 58k

2022

Construction Costs (incl abnormals)

Abnormal Costs

Average Cost Per Unit €

Range of Costs per Unit €

Average Cost Per Unit €

Range of costs per unit €

1bed house

251,604

144k - 311k

26,924

14k - 67k

2bed house

265,796

169k - 375k

33,581

8k - 67k

3bed house

317,667

205k - 429k

36,646

12k - 70k

4bed house

339,046

252k - 432k

31,360

21k - 50k

1bed apartment

246,302

198k - 363k

28,667

15k - 62k

2bed apartment

304,030

177k - 369k

30,073

9k - 62k

3bed apartment

410,417

268k - 451k

43,686

30k - 48k

* Construction Costs as shown, are derived from unit cost analysis and capture the construction cost element only, incl. abnormals (i.e. not all-in costs)
The above costs relate to the construction element of the all-in delivery cost. Other items that make up the all-in total include:
- Design/technical fees : Design fees vary from project to project, depending on the location, size and complexity of a scheme (and depending on whether design services are provided by a local authority in-house or via external appointment). As a guideline/indicator, design fee are generally expected to range between 7.5% to 12.5% of construction costs.
- Land cost : Land costs will vary significantly from project to project, depending on location and ownership status (i.e. land costs could vary from existing local authority land at no cost to land purchased at market value).
- Utilities : Connection fees for Irish Water, ESB, gas, etc. As a guideline/indicator, utility connection costs are generally in the order of €7k per unit.
- Other Costs : Other items that make up the all-in delivery cost can include site investigations/surveys, archaeological requirements, Percent for Art contributions - and will vary from scheme to scheme.
It is understood by all involved in advancing social housing projects that a range of factors can impact on the costs for individual projects. Project-specific issues will always arise and will be central to how a project can be advanced and the costs for same. These factors are part of the regular engagement that happens between my Department and local authorities/AHBs which is focussed on facilitating the earliest possible delivery of new social homes that are both high quality and value for money. To that end, as well as sharing UCCs with local authorities, my Department has previously shared outline specifications for new social housing and has also recently issued a new 'Design Manual' which will guide local authorities, AHBs and their Design Teams/consultants, on the design of social housing site layouts and the internal layouts of individual social homes. These recent initiatives are important in the work to improve the quality, cost-effectiveness and pace of delivery of social homes and I look forward to continuing our work with our delivery partners to take advantage of these opportunities.
Top
Share