246. Deputy John Brady asked the Minister for Transport if he will provide a progress report on plans to construct a new coastguard station in Greystones, County Wicklow; if contracts have been signed for its construction; if he will provide a timeline for the delivery of the new station; and if he will make a statement on the matter. [12620/23]

View answer

Written answers

My Department is responsible for the Irish Coast Guard building programme – essentially aimed at ensuring facilities for Coast Guard Units along the coast are fit for purpose. The programme is managed through the Office of Public Works (OPW) from planning design to build and on-going maintenance, with legal assistance as necessary from the Chief State Solicitor’s Office.

The Greystones project is a priority build on the Building Programme for the IRCG. It has been the subject of a number of significant revisions in terms of plans primarily owing to excessive cost and affordability. The location of the site identified for the new Coast Guard station has also presented challenges particularly in terms of the requirement to ensure adequate storm resilience.

The Office of Public Works are currently engaging with Wicklow County Council with regard to the final requirements of the site acquisition and plan development. Once these final matters are resolved the OPW will progress to tender and construction at the site with an expected commencement of works during Q4 2023.