Schools Building Projects

Dáil Éireann Debate, Tuesday - 21 March 2023

Tuesday, 21 March 2023

Questions (608)

Richard Boyd Barrett

Question:

608. Deputy Richard Boyd Barrett asked the Minister for Education the reason for the expected delay in going to tender to build a new permanent school (details supplied) to Q2 2024, adding a year to the potential opening date; and if she will make a statement on the matter. [12314/23]

View answer

Written answers

The school building project for the school referred to by the Deputy is being delivered under my Department's school building programme and will provide a 16 classroom primary school and accommodation, including two classrooms for children with special educational needs.

My Department progressed 8 Design & Build (D&B) projects (Lots 1 & 2) to construction in 2021, with a further 10 projects (Lots 3, 4 & 5) progressed to construction in Summer 2022. A further 10 projects (Lot 6) are due to proceed to tender next.

All of these projects are tendered to my Department’s current D&B Contractors Framework. It will be 2024 before the next scheduled bundle of projects (Lot 7) can be tendered to that framework and into late 2024 before further projects could proceed to tender.

In order to have projects delivered at the earliest possible opportunity, my Department is of the view that the intervening period can be utilised to bring a number of projects with planning permission, including the project for the school referred to by the Deputy, to the level of employer-led design with a Design Team assigned to do so under the supervision of my Department’s project manager. This will ensure that such projects do not have to await capacity on the current framework to proceed to tender but rather can be progressed and actioned over that timeframe to tender outside of the D&B framework.

It is envisaged that this will also serve to broaden the range and number of Contractors to which such projects can be tendered than would hitherto have been possible within the Design & Build Framework. This forms part of my Department’s ongoing strategic approach to seek to widen the pool of Contractors tendering for school building projects.

My Department’s Project Manager will be tasked with appointing Design Teams to these projects from my Department’s newly established Frameworks of Consultants with the expectation that these projects could then proceed to tender in early to mid-2024.

My Department will continue to liaise with the school’s patron body in relation to the school’s interim accommodation needs pending delivery of the permanent accommodation for the school and will provide further updates as the project progresses.