Renewable Energy Generation

Dáil Éireann Debate, Wednesday - 19 April 2023

Wednesday, 19 April 2023

Questions (15, 18)

Darren O'Rourke

Question:

15. Deputy Darren O'Rourke asked the Minister for the Environment, Climate and Communications the figures for all solar installations under all SEAI schemes in Q1 this year, in tabular form; and if he will make a statement on the matter. [18598/23]

View answer

Darren O'Rourke

Question:

18. Deputy Darren O'Rourke asked the Minister for the Environment, Climate and Communications the average waiting time for solar installation under all SEAI schemes in Q1 of 2023, in tabular form; and if he will make a statement on the matter. [18611/23]

View answer

Written answers

I propose to take Questions Nos. 15 and 18 together.

Below please find a table with the requested information provided by the SEAI:

Applications Received in Q1 2023 

Applications Paid in Q1 2023 (1) 

Average Time from Application to Approval  

Average Time from Approved Application to Receipt of Payment Request for Q1 2023 (4) 

Solar PV 

 4698 

3985 

Immediate (2) 

121 days 

Community Grants 

 12 

12 

No data available (3) 

No data available (3) 

One Stop Shops 

108 

47 

Immediate (2) 

139 days 

Non-Domestic Microgen 

 46 

 N/A Q1 

8 weeks 

 N/A Q1 

Note applications paid in Q1 do not necessarily relate to the applications received in Q1 as it is solely a matter for the applicant to get the works completed once they have an approved application. See note (3) for Community Energy Grants.

For the Solar PV and One Stop Shop schemes – approval of application is immediate once all eligibility criteria are met.

In the case of Community Energy Grants – the approval process relates to the larger community wide project and discrete homes are ultimately only identified to SEAI at time of request grant payment. Hence, in the case of Community Energy Grants, applications and payments relate to the same completed homes.

Note that the average time between application and request for payment is solely a matter for the applicant and their own decisions in respect of scheduling the works with their selected contractor

Question No. 16 answered with Question No. 13.
Question No. 17 answered with Question No. 13.
Question No. 18 answered with Question No. 15.