Dáil Éireann Debate, Tuesday - 25 April 2023

Tuesday, 25 April 2023

Questions (661)

Catherine Connolly

Question:

661. Deputy Catherine Connolly asked the Minister for Rural and Community Development further to Parliamentary Question No. 42 of 23 February 2023, the status of the development of the pier on Inis Oírr; the status of the CPO process; and if she will make a statement on the matter. [19420/23]

View answer

Written answers

As the Deputy is aware, Galway County Council is the responsible authority for the maintenance and development of Inis Oírr pier. A steering committee consisting of representatives from my Department, Galway County Council and the Consulting Engineers meets regularly to monitor progress on the work being undertaken. The most recent meeting took place last week.

Galway County Council published the Compulsory Purchase Order (CPO) for the land required for construction of the pier in December 2022 and submitted it to An Bord Pleanála. The CPO was subsequently approved by An Bord Pleanála, and the full CPO was published in The Connacht Tribune on 07 April. Landowners also received letters and maps on this date.

The CPO becomes operative from 28 April, at which point all affected landowners will be notified via letter again. A review period of 8 weeks will then follow, until 2 June.

Currently, Galway County Council are finalising the documents for the construction tender with a view to them being ready for publication as soon as possible following confirmation of the CPO.