422. Deputy Alan Kelly asked the Minister for Housing, Local Government and Heritage if the three local authority housing units approved for construction in Cloughjordan, County Tipperary, in May 2015 have finished construction; if so, the project completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [22953/23]

View answer

Written answers

Tipperary County Council revised the number of new social homes for the project at Cloughjordan from 3 to 2 units in 2016 and they reported it as completed in Q2 of 2021.  The project received funding of €472,303 from my Department.

My Department publishes quarterly Social Housing Construction Projects Status Reports (CSR), which provide details of social housing developments that have been completed, are under construction or are progressing through the various stages of design and tender processes. The CSR setting out the position at end Q2 2021 can be found on my Department’s website at the following link; 

CSR Status Report Q2 2021

The full set of published CSR reports can be found at this link:

www.gov.ie/en/collection/cb885-social-housing-construction-projects-status-reports/

I am not aware of this project being officially opened.