My Department issued Stage 3 Pre-tender Approval for this project on 22 December 2022.

Kerry County Council have advised that it is being advanced under the Social Housing Investment Programme (SHIP) and that they expect that a Stage 4 Approval to Proceed (to contract award) submission will be issued to the Department in June 2023.

Should the project proceed to receive Stage 4 approval, work is due to commence on site in July 2023 with completion estimated for April 2025.