Skip to main content
Normal View

Energy Production

Dáil Éireann Debate, Tuesday - 13 June 2023

Tuesday, 13 June 2023

Questions (221, 222, 223)

Ged Nash

Question:

221. Deputy Ged Nash asked the Minister for the Environment, Climate and Communications the costs to date of providing emergency power generation under the measures carried out as part of the consent granted to the CRU in June 2021 under Article 28(10) of the European Communities (internal Market in Electricity) Regulation and as part of the Development (Emergency Electricity Generation) Act 2022; if he will break these costs down by development, supply and build contract and connection costs; if he will outline how these costs compared to initial estimates and quotations received; what the initial anticipated budget for this provision was; and if he will make a statement on the matter. [28224/23]

View answer

Ged Nash

Question:

222. Deputy Ged Nash asked the Minister for the Environment, Climate and Communications what level of oversight his Department has in the provision of emergency power generation nationally; which body is in charge of managing the cost and delivery of these projects; how regularly this body reports on costs or costs overruns and progress in the delivery of this emergency power generation to his Department; and if he will make a statement on the matter. [28225/23]

View answer

Ged Nash

Question:

223. Deputy Ged Nash asked the Minister for the Environment, Climate and Communications what he expects the all-in costs to the Exchequer are in terms of (euros per MWHr) of emergency electricity generation vs new-build electricity generation contracted under the recent capacity market auctions conducted in 2022 and 2023; and if he will make a statement on the matter. [28226/23]

View answer

Written answers

I propose to take Questions Nos. 221 to 223, inclusive, together.

The Commission for Regulation of Utilities (CRU) which has statutory responsibility to ensure security of supply, has the duty to monitor electricity supplies and to take sure measures as it considers necessary to protect the security of supply. It is assisted in its role by EirGrid, which is required to report to the CRU regarding security of electricity supply matters. EirGrid is also responsible for daily management of the electricity system.

The provision of Temporary Emergency Generation (TEG) under the CRU Security of Supply programme is carried out by EirGrid under direction from CRU further to Ministerial consent; thus EirGrid are responsible for managing the delivery of the TEG.

EirGrid provides updates to the Electricity Security of Supply programme on a regular basis with the Steering Group generally meeting on a monthly basis, and with working level meetings occurring more frequently. The TEG projects continue to be delivered and EirGrid report that they are expected to begin providing service across Winter '23/'24 on a phased basis.

The Commission for the Regulation of Utilities has advised that significant elements of the Temporary Emergency Generation projects remain under commercial negotiation at this time and therefore total cost certainty is not available.

Concerning Exchequer funding, following on from the EirGrid Act 2022, the Exchequer provided two supplementary estimates to enable delivery of these projects – €200m in July and €150m in October 2022. The Department authorised €151m of the amount allocated for release to EirGrid in line with contractual progress by end year 2022 and the balance was returned to the Exchequer. The Exchequer allocation does not equate to the total project costs. Further Exchequer funding is neither budgeted for nor at this time deemed to be required in 2023 to enable completion for these projects.

Question No. 222 answered with Question No. 221.
Question No. 223 answered with Question No. 221.
Top
Share