403. Deputy Alan Dillon asked the Minister for Public Expenditure, National Development Plan Delivery and Reform if Castlebar Garda station or any Mayo Garda stations have been identified as a recipient of such funding to support its expansion and infrastructure development; and if he will make a statement on the matter. [27430/23]

View answer

Written answers

The Office of Public Works can confirm that the table below includes all works where costs exceed €50,000, completed, ongoing or planned to Garda Stations in County Mayo in 2023 and 2024, to be carried out by OPW and funded by An Garda Síochána. The relevant Garda Station along with the nature and status of the works is outlined in the table below.

Garda funded works, with costs in excess of €50,000, that are completed, ongoing, or planned to be carried out by OPW at Garda Stations in County Mayo in 2023 and 2024

Station

Description of works

Status

Castlebar GS

Sanitary Facilities Upgrade

Planned to tender 2023

Ballina GS

Custody Suite Upgrade

Planned to tender 2023

Claremorris GS

Custody Suite Upgrade

Planned to tender 2023