Housing Provision

Dáil Éireann Debate, Wednesday - 21 June 2023

Wednesday, 21 June 2023

Questions (114)

Ivana Bacik

Question:

114. Deputy Ivana Bacik asked the Minister for Housing, Local Government and Heritage if the ten AHB housing units approved for construction in an area (details supplied) in July 2015 have finished construction; if so, their completion date; the final number of units delivered; the total cost of the project; if the development was officially opened by a Minister; if so, when that happened; if not, the reasons for the project not proceeding; the current status of the project; and if he will make a statement on the matter. [29991/23]

View answer

Written answers

My Department publishes the Social Housing Construction Status Report (CSR), which provides details of social housing developments that have been completed, are under construction or are progressing through the various stages of design and tender processes. The most recent CSR (Quarter 4 2022) and previous reports are  available at the following links:

www.gov.ie/en/publication/14f82-social-housing-construction-projects-status-report-q4-2022/

www.gov.ie/en/collection/cb885-social-housing-construction-projects-status-reports/

In Q2 2023, my Department granted a revised Stage 3 Pre -Tender Approval for this project which is being progressed under the Capital Assistance scheme. This approval is subject to a number of conditions, including clarification around the scheme design. The Department is actively engaged with South Dublin County Council to progress this project to construction.