Skip to main content
Normal View

Schools Building Projects

Dáil Éireann Debate, Tuesday - 27 June 2023

Tuesday, 27 June 2023

Questions (314)

Sorca Clarke

Question:

314. Deputy Sorca Clarke asked the Minister for Education when construction works at a school (details supplied) will be completed; and the estimated cost of this project. [31089/23]

View answer

Written answers

The Letter of Acceptance (LOA) for the school referred to by the Deputy issued to the preferred tenderer on the 1st July 2022 commencing the school building contract.

Works are progressing well on site and phase one of the school building is due for completion in Quarter 1, 2024.

My Department will continue to liaise with the school and their Patron Body in relation to interim accommodation needs pending delivery of their permanent accommodation.

The estimated cost of the project is some €32m.

Top
Share