Skip to main content
Normal View

Schools Building Projects

Dáil Éireann Debate, Thursday - 29 June 2023

Thursday, 29 June 2023

Questions (137)

Aindrias Moynihan

Question:

137. Deputy Aindrias Moynihan asked the Minister for Education the up-to-date position on delivering new school buildings for a school (details supplied); and if she will make a statement on the matter. [31666/23]

View answer

Written answers

The project to which the Deputy refers has been devolved for delivery to Cork Education and Training Board (CETB).

I am pleased to advise that the Stage 2a or detailed design meeting took place at the end of November 2022. Officials from my Department met with Cork ETB and the full Design Team where a number of recommendations were made. The design team was requested to address these recommendations and comments and to submit a Stage 2A addendum report. My Department understands from CETB that its design team is currently finalising this Report and the submission is imminent. Subject to the Department being satisfied with this report, approval to progress to Stage 2b (planning) will be sanctioned.

The next step for CETB and its Design Team will be to obtain the requisite statutory planning approvals. The project can then be expected to move onward to tender and construction in due course. CETB will be engaging directly with the school to keep it informed of progress.

Top
Share