In March 2022 my Department issued Stage 1 approval to Dublin City Council for the redevelopment of Blocks L, M and N at Oliver Bond House. In June 2023 my Department received a revised Stage 1 submission which is currently under consideration.
My Department is not in a position to release the amount of funding approved or requested at this early stage (Stage 1) as this is subject to change as the project progresses through the pre-construction process including design and costings, planning approval and public procurement/tendering.
In addition to funding provided by the local authorities themselves in respect of their own housing stock, my Department provides funding across a number of programmes to support the local authority work to maintain and improve their social housing stock. It is a matter for the local authority to identify their priorities and make submissions for funding consideration under the various schemes to my Department.