The project to which the Deputy refers has been devolved to the National Development Finance Agency (NDFA) for delivery as part of a programme of school building projects. This school is in the bundle referred to as ‘Project Boyne’
The project, which is to be built on the site adjacent to the school, is currently at Stage 2b (planning) of the architectural process. A planning application was lodged with Wicklow County Council and planning permission was granted in Quarter 4 2022. Further surveys aimed at informing the works requirements for this project were carried out in Q1 2023 and reports are currently being finalised.
When Stage 2b has been approved, the next stage is tendering for a contractor and then onwards to construction. It is not possible to provide a date for the practical completion of the project in advance of the outcome of the required procurement process. The NDFA will be engaging directly with the school authority to keep it informed of progress.