93. Deputy Aindrias Moynihan asked the Minister for the Environment, Climate and Communications the up-to-date position on national broadband plan roll-out across County Cork when (details supplied) can expect the service to be available; and if he will make a statement on the matter. [41607/23]

View answer

Written answers

In December 2022, my Department published Ireland's Digital Connectivity Strategy which supports the ambition outlined in the National Digital Strategy and sets out a number of ambitious targets, including that:

• all Irish households and businesses will be covered by a Gigabit network no later than 2028;

• all populated areas will be covered by 5G no later than 2030, and

• digital connectivity will be delivered to all schools and broadband connection points by 2023.

These targets will be achieved through commercial operators investing in their networks, complemented by the State’s National Broadband Plan (NBI).

Commercial operators’ fibre rollouts are progressing at pace. Open eir, as part of their IFN fibre programme currently rolling out nationwide, plan to connect over 1.9m premises to their commercial fibre network by 2026. Open eir have already passed over 136,000 homes and businesses with access to gigabit services in Co. Cork, with plans to pass a further c.76,000 premises over the next 2 – 3 years, bringing their total fibre-based investment in the county to over €89m. Other commercial operators are also continuing to increase their network footprint across County Cork, with SIRO recently passing more than 533,000 premises and Virgin Media passing almost 70,000 premises.

National Broadband Ireland (NBI)is currently rolling out of a high speed and future-proofed broadband network to primarily rural areas through its Contract with the Minister. The intervention area covers over 1.1 million people living and working in over 560,000 premises, including almost 100,000 businesses and farms along with some 679 schools.

I am advised by NBI that, as of 15th September 2023, 182,250 premises are passed across 26 counties and available for immediate connection. 53,695 premises are already connected to the NBP high-speed broadband network. In County Cork, over 22,000 homes and businesses have been passed by NBI and are available for immediate connection, with c. 6,545 of those now connected to the NBP State Intervention network.

My officials have reviewed the Dripsey and Berrings areas referred to in the question and we understand eir will deliver fibre to the home services to Dripsey in the foreseeable future. My Department has asked eir for a delivery date for this. Once more information is received from eir we will revert.

In the Berrings area I understand eir plans to upgrade that area with fibre to the home over the coming 2-3 years and I understand all premises marked “Blue” are part of the eir upgrade. For those premises marked Amber in that area we have been advised by NBII that it may be 2025/26 before fibre can be ordered.

Broadband Connection Points (BCPs) are a key element of the NBP providing high speed broadband in every county in advance of the roll out of the fibre to the home network. As of 15th September some 950 sites have been installed by NBI and the high speed broadband service will be switched on in these locations through service provider contracts managed by the Department of Rural and Community Development for publicly accessible sites and the Department of Education for school BCPs.

The closest Broadband Connection Point in Berrings is located at Courtbrack Community Centre, Cork, T23 NH22, which is now connected to high speed broadband. This is located approximately 4.8 km from Berrings National School and provides an option for local residents to access quality broadband for free. Further details can be found at nbi.ie/bcp-locations/.

Further details are available on specific areas within County Cork can be monitored via nbi.ie/reps. A county update can be selected to provide the overall number of premises in the Intervention Area, the overall NBP investment in the county, the number of premises passed and connected to date and the status of each of the Deployment Areas with the anticipated date for connection over the lifetime of the project. NBI has a dedicated email address, reps@nbi.ie, which can be used by Oireachtas members for specific queries.

Recent ComReg data shows that Quarter 2, 2023 saw a 7.4% increase in fibre broadband subscriptions compared to the first 3 months of the year, and a 33.7% increase when compared to Quarter 2 of 2022. This demonstrates that take-up of fibre connectivity for homes and businesses is increasing massively as it’s deployed to areas where it had previously been unavailable. The same ComReg data also indicates that c.40% of homes and business throughout the State now have access to gigabit services through either fibre or cable infrastructure and this continue increase month on month as operators continue to invest heavily in gigabit networks across the State.