Flood Risk Management

Dáil Éireann Debate, Tuesday - 17 October 2023

Tuesday, 17 October 2023

Questions (181)

Pauline Tully

Question:

181. Deputy Pauline Tully asked the Minister for Public Expenditure, National Development Plan Delivery and Reform the flood relief projects currently under construction and funded by the OPW; and when each of these flood relief projects will be completed, in tabular form. [45291/23]

View answer

Written answers

The Government has committed €1.3 billion to the delivery of flood relief schemes over the lifetime of the National Development Plan to 2030 to protect approximately 23,000 properties in communities that are under threat from river and coastal flood risk.  Since 2018, as part of a phased approach to scheme delivery, this funding has allowed the OPW to increase its work on flood relief schemes to over 90 schemes at design and construction at this time.  

There are currently seven flood relief schemes at Construction Stage.  The following table lists these schemes and their anticipated substantial completion dates. 

OPW Flood Relief Scheme

Substantial Completion

Athlone Flood Alleviation Scheme

Q2 2024

Dodder Phase 2C, 2D, 2E Flood Relief Scheme

Q4 2023

Glashaboy (Glanmire / Sallybrook) Flood Relief Scheme

Q4 2026

Morell River Flood Management Scheme

Q4 2025

River Mall (Templemore) Flood Relief Scheme

Q2 2024

Springfield Flood Relief Scheme

Q2 2024

Whitechurch Stream Flood Alleviation Scheme

Q4 2025