179. Deputy Rose Conway-Walsh asked the Minister for Public Expenditure, National Development Plan Delivery and Reform the total projected capital spend in 2023, broken down by core and non-core and what it represents as a percentage share of Total Government spending and core spending; and if he will make a statement on the matter. [45864/23]

View answer

Rose Conway-Walsh

Question:

180. Deputy Rose Conway-Walsh asked the Minister for Public Expenditure, National Development Plan Delivery and Reform the total projected capital spend in 2024, broken down by core and non-core and what it represents as a percentage share of total Government spending and core spending; and if he will make a statement on the matter. [45871/23]

View answer

Rose Conway-Walsh

Question:

181. Deputy Rose Conway-Walsh asked the Minister for Public Expenditure, National Development Plan Delivery and Reform the total projected capital spend in 2025; what it is projected to represent as a percentage share of total Government spending and core spending; and if he will make a statement on the matter. [45865/23]

View answer

Written answers

I propose to take Questions Nos. 179 to 181, inclusive, together.

As Minister for Public Expenditure, NDP Delivery, and Reform I am responsible for setting the overall capital allocations across Departments.  Over the lifetime of this NDP out to 2030, the government is investing €165 billion in new and upgraded infrastructure that will meet the needs of our growing population.  This year alone over €12 billion will be invested from the Exchequer in vital infrastructure projects.  The NDP includes agreed Exchequer allocations for each Department for a five year period (2021 to 2025) and the overall capital expenditure ceilings out to 2030.

The following table sets out total allocated capital expenditure as a percentage of total current and capital expenditure for the period 2023 – 2025. Total allocated capital expenditure is as set out in the National Development Plan 2021-30. Additional capital expenditure of €0.25 billion is also included for 2024 along with an additional €0.75 billion in 2025 from windfall exchequer receipts, to be allocated to critical infrastructure projects that are at an advanced stage.

Year

Total Capital

€,m

Of which Core

€,m

Of which non-Core

€,m

Capital  as % of Total Current and Capital Spending

2023

12,100

11,566

534

13.0%

2024

13,103

12,560

543

13.6%

2025

14,352

13,442

910

14.8%

Question No. 180 answered with Question No. 179.
Question No. 181 answered with Question No. 179.