Schools Building Projects

Dáil Éireann Debate, Thursday - 19 October 2023

Thursday, 19 October 2023

Questions (189)

Catherine Connolly

Question:

189. Deputy Catherine Connolly asked the Minister for Education the timeline for when the promised modular building to accommodate the ASD unit at a school (details supplied) with be delivered and operational; the details of any engagement her Department has had with the property management company in this regard; the details of any engagement her Department has had with the school management and parent representatives with regard to the delay in delivering the promised modular building; and if she will make a statement on the matter. [45849/23]

View answer

Written answers

I am pleased to advise the Deputy that approval under the Additional School Accommodation scheme issued to the school in question for the provision of a 1 x 100m2 SEN classroom. 

Although this project is devolved for delivery to the school authority, the Department arranged a project manager under its procurement framework to assist the school authority in the delivery of its building project. This is designed to enable the accommodation to be provided as quickly as possible and help ease the administrative workload for school authorities in relation to the management and delivery of projects. The use of the Department’s Modular Accommodation Framework also assists in ensuring lead in periods for procurement of this modern method of construction are minimised to the greatest extent possible. To date, this has worked very well in the education sector and has seen delivery of large scale, high quality modular accommodation to meet the needs of children, particularly those with special educational needs.

However, the wider context in relation to the overall modular market at present is challenging with modular accommodation suppliers being very busy across commercial, housing and other sectors.  The Department is working closely with the Project Management teams and the modular accommodation suppliers to ensure additional capacity for the schools sector is delivered as quickly as possible. The Department has been assured by the relevant project manager for the school in question that regular communication with the school authority is ongoing.  Expected start date on-site for this project is 3-5 weeks.

The School Authority has devolved responsibility for delivery of this project.