25. Deputy Pádraig O'Sullivan asked the Minister for Public Expenditure, National Development Plan Delivery and Reform if any additional or emergency funding will be provided to the Glashaboy flood relief scheme following severe and unprecedented flooding in Cork; if his Department will propose any new flood relief schemes for Cork; and if he will make a statement on the matter. [46783/23]

View answer

Written answers

The Office of Public Works (OPW) in partnership with Cork City Council are engaging proactively to progress the Glashaboy flood relief scheme for Glanmire.

The Glashaboy Flood Relief Scheme was confirmed in January 2021 by the Minister for Public Expenditure, National Development Plan Delivery and Reform under the Arterial Drainage Acts 1945 to 1995. The scheme is being funded from the €1.3 billion in flood relief measures under the National Development Plan to 2030, and as part of Project Ireland 2040.

The scheme, when complete, will provide flood protection to some 103 properties; 78 residential properties and 25 commercial premises and will address the flood risk in a number of locations in the Glanmire area. The scheme will include defences, such as walls and embankments; culvert upgrades; channel widening and road re-grading.

In April 2023, Cork City Council, following a successful tender competition, awarded the civil works contract to Sorensen Civil Engineering. In July 2023 Sorensen Civil Engineering mobilised on site carrying out site investigation works, working with utility providers to agree diversions and engaging with stakeholders with works commencing on site at Cúil Chluthair and Springmount.

The construction programme is anticipated to take 32 months with the works split up into several Zones to minimise disruption to the public and businesses. The schedule for the next 3 months of work is available on a dedicated webpage on the project website which has been set up to provide updates to the public throughout the works.

The total project budget for Glashaboy is €38m. Throughout all scheme-delivery stages, project budgets of flood relief schemes are continually monitored and reviewed. Any additional costs encountered due to the recent flood event will be assessed and managed as part of this process on the Glashaboy Flood Relief Scheme. Budgets are reviewed and monitored throughout each stage to ensure that the scheme is executed satisfactorily, to standard and on time.