Dáil Éireann Debate, Tuesday - 14 November 2023

Tuesday, 14 November 2023

Questions (156)

Paul Donnelly

Question:

156. Deputy Paul Donnelly asked the Minister for Public Expenditure, National Development Plan Delivery and Reform the Garda stations within the DMR that are scheduled for refurbishment by the OPW between now and the first half of 2024; the nature of the refurbishment, per station, in tabular form; and if known, when refurbishment works will commence. [49861/23]

View answer

Written answers

I can confirm that the Office of Public Works has scheduled refurbishment works to Garda Stations within the DMR to be carried out between now and the first half of 2024.

The Garda Stations and the nature of the works to be carried out are outlined in the table below and include only works valued in excess of €150,000. The works outlined relate to works funded both by OPW and An Garda Siochána.

The Commencement dates for the scheduled works are subject to the final sign off of operational and design requirements by An Garda Síochána and where necessary, successful tendering process.

Garda Station

Nature of the works

Works Due for Commencement

Cabra GS

Refurbishment/ reconfiguration of portacabins to rear.

Q2 2024

Lusk GS

Reconfiguration and upgrade of station, including conversion of married quarters

Q2 2024

Swords GS

Reconfiguration of 2 rooms at first floor level to provide new canteen and kitchen area

On site, to complete end 2023/ early 2024

Finglas GS

Investigation and repair of pre tensioned glass façade to tower

On site, to complete end 2023/ early 2024

Malahide GS

Maintenance works to attics and large scale roof repair to valleys.

On site, to complete end 2023/ early 2024

Malahide GS

Refurbishment of cast iron railings, painting / refurbishment of façade and windows

Q2 2024

Raheny GS

Structural repair works to 2 storey block, including underpinning, works to brickwork façade, and new footpath.

Q3 2024

Crumlin GS

Prisoner Processing Area Spec Upgrade

Q2 2024

Sundrive Rd GS

Public Office Refurbishment

Q2 2024

Greystones GS

Boundary Wall repairs and car park resurfacing

Q1 2024