Dáil Éireann Debate, Thursday - 23 November 2023

Thursday, 23 November 2023

Questions (218)

Emer Higgins

Question:

218. Deputy Emer Higgins asked the Minister for Education the updated timeline for the delivery of a new school accommodation for post-primary schools (details supplied), given the tender process has been completed; and if she will make a statement on the matter. [51774/23]

View answer

Written answers

The school building project for the school referred to by the Deputy will deliver a new 1,000 pupil post-primary school and accommodation, including four classrooms, for children with special educational needs.

This project is being delivered under my Department’s Design and Build Programme and is currently at tender stage.

The Invitation to Tender issued on the 18th April 2023, as part of a bundle of projects issued to a Framework of Design & Build Contractors. The tender process currently takes approximately 8-12 months. Once a Contractor has been appointed, it is anticipated that construction would commence shortly thereafter.