341. Deputy Catherine Murphy asked the Minister for Education the date on which and/or if she will provide additional Portakabin arrangements to be installed in schools in Prosperous and Clane where necessary to ensure that all children currently on a waiting list will receive a school place in 2024 and 2025. [55179/23]

View answer

Written answers

As the Deputy may be aware, for school planning purposes, my Department divides the country into 314 school planning areas and uses a Geographical Information System (or GIS) to anticipate school place demand. Information from a range of sources, including Child Benefit Data, school enrolment data and information on residential development activity is used for this purpose. In addition, Project Ireland 2040 population and housing targets inform the Department’s projections of school place requirements.

Having considered the projected requirements in each school planning area, including the Prosperous School Planning Area, my Department then makes an assessment of the existing capacity and identifies any requirement for additional provision. Additional provision is made as necessary, where the existing capacity is insufficient for future needs.

The Department is aware of pressures for school places in the Prosperous_Clane School Planning Area. A critical next step is to acquire clarity on the actual number of additional first year places required for 2024 in order for an appropriate solution to be put in place. In that context, schools in a number of areas of enrolment pressure, including Prosperous School Planning Area, have been requested to share data on applications for admissions. The Department is liaising closely with schools to ensure that this data is provided as soon as possible, and once it is received the actual requirement for places can be established. The Department is already having discussions with the relevant school patrons and authorities regarding potential solutions but the understanding of the actual school place needs will give clarity as to the specific actions that are required.

This close engagement with schools and patrons will also allow the Department to identify particular further capacity requirements for the forthcoming years and put any required solutions in place - beyond those that are already in train - to ensure sufficient school places to meet the needs of students in the area.

My Department has invested significantly in schools in County Kildare over recent years. Under the National Development Plan, a total of almost €250m has been invested in schools in County Kildare over the last five years. This investment has focused on provision of additional capacity to cater for its increasing population and there are further significant projects in our pipeline including for the Prosperous School Planning Area.

These projects include a number of further new school buildings and extensions are at construction or planned, including a new school buildings in Prosperous School Planning Area.

The Capital Programme details the school projects that are being progressed under Project Ireland 2040. The current status of large-scale projects being delivered under Project Ireland 2040, including projects in the school planning areas in question, may be viewed on my Department's website at, www.gov.ie and this information is updated regularly. In addition, a list of large-scale projects completed from 2010 to date may also be viewed on the website.

I can assure the Deputy that Department officials will continue to actively engage with schools and patrons to ensure that there is appropriate provision for all students across Prosperous School Planning Area for the 2024/25 school year and into the future.