569. Deputy Peadar Tóibín asked the Minister for Justice the number of tribunals, public investigations and commissions of investigations in process; the length of time each has been underway; when each will conclude; the cost to date of each; and the estimated cost of each at completion. [44814/23]

View answer

Written answers

There is currently one Commission of Investigation in process by my Department. The details of this, as requested by the Deputy, are outlined below.

Length of Time Underway

Conclusion Date

Cost To Date

Estimated Cost at Completion

Hickson Commission of Investigation

Commenced November 2018 - expected to complete in mid- 2024

N/A

3,113,076.66

*The work of the Commission is ongoing and is expected to be completed in mid-2024. It is not possible to provide the estimated costs at completion as any estimation given would be speculative.