Schools Building Projects

Dáil Éireann Debate, Wednesday - 13 December 2023

Wednesday, 13 December 2023

Questions (89)

Cormac Devlin

Question:

89. Deputy Cormac Devlin asked the Minister for Education if she will provide an update on a school building project (details supplied); and if she will make a statement on the matter. [55457/23]

View answer

Written answers

I am pleased to inform the Deputy that the school in question was approved funding under my Department’s Additional School Accommodation (ASA) scheme for the provision of 9 mainstream classrooms, 2 SET rooms, 2 classroom SEN base and ancillary.

My Department received a pre stage 1 report, and requested further clarification on some aspects of the information submitted directly with the Design Team. This has now been received and is currently under review by my Department's Professional and Technical team and communications will issue to the school directly once this review has been completed.

Whilst this project has been devolved to the school authority for delivery, my Department will continue to engage directly with the school to provide whatever practical assistance and advice is necessary to implement this important project for the wider school community.