Schools Building Projects

Dáil Éireann Debate, Wednesday - 17 January 2024

Wednesday, 17 January 2024

Questions (474)

Matt Carthy

Question:

474. Deputy Matt Carthy asked the Minister for Education further to Parliamentary Question Nos. 218 of 10 October 2023 and 464 of 7 November 2023, when the review of the Stage 2A report will be completed in respect of the application by a school (details supplied) regarding the proposed permanent extension; if she will expedite this review; and if she will make a statement on the matter. [56388/23]

View answer

Written answers

I can confirm to the Deputy that my Department received a Stage 2A report for review by my Department's Professional and Technical team. Officials from my Department have been in contact with the school in recent days to advise on how best to address some of the issues that were identified with this project. 

A revised Stage 2A report has now been requested from the Design Team.

The school authority is being assisted by Cavan and Monaghan ETB (CMETB) in the delivery of this project and it is now with the school authority and CMETB to progress this project accordingly.