Schools Building Projects

Dáil Éireann Debate, Tuesday - 23 January 2024

Tuesday, 23 January 2024

Questions (303)

Denise Mitchell

Question:

303. Deputy Denise Mitchell asked the Minister for Education the status of the works being carried out at a school (details supplied). [2970/24]

View answer

Written answers

The large scale capital project at the school is for the provision of a new 600 pupil school and ancillary accommodation. The project is at Architectural Planning Stage 3 – Tender Action and Award.

The original grant of planning expired in December 2022, but due to changes to the Planning Acts in September 2021, it was no longer possible to apply for an extension to the planning permission for the main building project and a new application was required. The new planning permission application was lodged, and subsequently granted in December 2023, with a number of conditions attached.

The Design Team are examining the implications of these conditions.

My Department officials will be in contact with the School authority when the Design Team complete their review.